task list

Leanne Gray

Date Task Complete By Effort % Progress
01/23 Ponder iteration task breakdown and schedule 01/29 15:30 1 hour 100%
01/30 Research FMOD and prepare slides 02/05 15:30 4 hours 100%
02/05 Add a hovering object to the world with Cole 02/12 15:30 4 hours 100%
02/13 Integrate object and sound code into the svn trunk with Cole 02/20 09:30 2 hours 100%
02/20 email presentation (including ev data and effort pie charts) to Cole 02/25 17:00 2 hours 100%
02/27 research proximity detection in OGRE 03/06 09:30 90 minutes 100%
03/06 create slides about proximity detection in Ogre 03/13 09:30 60 minutes 100%
03/13 create OCL 03/20 09:30 120 minutes 100%
03/13 test and integrate proximity detection code 03/27 09:30 120 minutes 100%
03/27 email presentation (including ev data and effort pie charts) to Cole 04/01 17:00 120 minutes 100%
04/03 create posterboard for open house 04/10 10:30 60 minutes 100%
04/10 show up for open house 04/14 09:00 360 minutes 100%
04/15 update Ogre libraries and get code to compile 04/22 23:59 360 minutes 100%
04/22 test code and create slides 04/27 17:00 120 minutes 100%
04/27 create ev slides and assemble presentation 6 04/29 17:00 120 minutes 100%

Ryan Hannebaum

Date Task Complete By Effort % Progress
01/23 Ponder iteration task breakdown and schedule 01/29 15:30 1 hour 100%
01/30 Research mouse control of camera with Alex 02/05 15:30 4 hours 100%
02/05 Continue researching mouse control and prepare slides with Alex 02/12 15:30 3 hours 100%
02/13 Implement mouse listener control with Alex 02/20 09:30 5 hours 100%
02/20 (with Alex) email mouse control slides to Leanne and check-in final copy of mouse control code to svn branch 02/23 17:00 3 hours 100%
02/27 research Matt's implementation of the textual output 03/06 09:30 90 minutes 100%
03/06 create slides about text output in Ogre 03/13 09:30 60 minutes 100%
03/13 create new text display 03/20 09:30 240 minutes 100%
03/13 test new text display 03/27 09:30 120 minutes 100%
03/27 create/submit slides for presentation 5 03/30 17:00 60 minutes 100%
04/03 create posterboard for open house 04/10 10:30 60 minutes 100%
04/10 show up for open house 04/14 09:00 360 minutes 100%
04/15 research methods of toggling sound/gui and create slides 04/22 23:59 240 minutes 100%
04/22 add the ability to toggle sound at runtime and test 04/27 17:00 120 minutes 100%
04/27 email toggling slides to Leanne 04/27 17:00 30 minutes 100%

Cole Hoosier

Date Task Complete By Effort % Progress
01/23 Ponder iteration task breakdown and schedule 01/29 15:30 1 hour 100%
01/30 Add EV table to website 02/02 23:59 30 minutes 100%
01/30 Research creating hovering objects and prepare slides 02/05 15:30 4 hours 100%
02/05 Add a hovering object to the world with Leanne 02/12 15:30 4 hours 100%
02/13 Integrate object and sound code into the svn trunk with Leanne 02/20 09:30 2 hours 100%
02/20 email OCL and UML slides to Leanne and prepare installer 02/23 17:00 2 hours 100%
02/25 prepare CD for presentation and update website 02/26 09:30 1 hours 100%
02/27 research proximity detection in OGRE 03/06 09:30 90 minutes 100%
03/06 create slides about proximity detection in Ogre 03/13 09:30 60 minutes 100%
03/13 create OCL 03/20 09:30 120 minutes 100%
03/13 test and integrate proximity detection code 03/27 09:30 120 minutes 100%
03/27 integrate UI svn branch into trunk 03/30 17:00 60 minutes 100%
03/27 create/submit slides for presentation 5 03/30 17:00 60 minutes 100%
03/27 prepare CD and website for presentation 5 04/02 08:30 120 minutes 100%
04/03 create posterboard for open house 04/10 10:30 60 minutes 100%
04/10 show up for open house 04/14 09:00 360 minutes 100%
04/15 update Ogre libraries and get code to compile 04/22 23:59 360 minutes 100%
04/22 test code and create slides 04/27 17:00 120 minutes 100%
04/27 email library, level, and camera slides to Leanne 04/27 17:00 60 minutes 100%
04/27 turn in cd 04/30 09:30 30 minutes 100%

Alex Stampbach

Date Task Complete By Effort % Progress
01/23 Ponder iteration task breakdown and schedule 01/29 15:30 1 hour 100%
01/30 Research mouse control of camera with Ryan 02/05 15:30 4 hours 100%
02/05 Continue researching mouse control and prepare slides with Ryan 02/12 15:30 3 hours 100%
02/13 Implement mouse listener control with Ryan 02/20 09:30 5 hours 100%
02/20 (with Ryan) email mouse control slides to Leanne and check-in final copy of mouse control code to svn branch 02/23 17:00 3 hours 100%
02/27 research Matt's implementation of the textual output 03/06 09:30 90 minutes 100%
03/06 create slides about text output in Ogre 03/13 09:30 60 minutes 100%
03/13 create new text display 03/20 09:30 240 minutes 100%
03/13 test new text display 03/27 09:30 120 minutes 100%
03/27 create/submit slides for presentation 5 03/30 17:00 60 minutes 100%
04/03 create posterboard for open house 04/10 10:30 60 minutes 100%
04/10 show up for open house 04/14 09:00 360 minutes 100%
04/15 research methods of toggling sound/gui and create slides 04/22 23:59 240 minutes 100%
04/22 add the ability to toggle sound at runtime and test 04/27 17:00 120 minutes 100%
04/27 email toggling slides to Leanne 04/27 17:00 30 minutes 100%

Old task list data