- Team Meeting (9/13)
- Target Operating System: Microsoft Windows
- Alternatives: Linux, OS X
- Rationale: Project already setup for Windows
- Development Environment: Visual Studio.NET
- Alternatives: cli/make
- Rationale: Some members already familiar with VS.NET
- Graphics Rendering Engine: OGRE
- Alternatives: none considered
- Rationale: Project statement requires Ogre, project already uses Ogre
- Hashed out ideas for our gameplan
- Target Operating System: Microsoft Windows
- Team Meeting (9/20)
- None
- Team Meeting (9/27)
- Outlined tasks until presentation 2
- Team Meeting (10/4)
- Revised gameplan to include lighting and terrain/sky fixes
- Team Meeting (10/11)
- Outlined tasks related to presentation 2 for the next week
- Revised gameplan to delineate between goals for this semester and next semester
- Attempting to increase robustness and reality this semester
- Moved "exciting" features to next semester
- Decided that "this Monday" refers to the monday of the current calendar week
- Example: If it's Wednesday and I say "this Monday", I am referring to the Monday 2 days ago.
- Alternatives: "This Monday" refers to the nearest Monday in the future
- Rationale: Matt and Cole like it better referring to the current week
- Rationale: "Last Monday" is confusing when it refers to the current calendar week.
- Team Meeting (10/18)
- Assigned slides for presentation 2
- Added goal of controlling camera view with the mouse for this semester to the gameplan
- Team Meeting (10/25)
- Moved weekly team meetings to Tuesday 18:30
- Revised the project schedule to include more subtasks
- Divided up tasks for the remainder of the semester
- Team Meeting (10/31)
- Demo'd team members' work from the last week
- Created testing plan that outlines unit testing and integration testing
- Assigned tasks until the next meeting
- Team Meeting (11/7)
- Reviewed team members' work from the last week
- No decisions made
- Team Meeting (11/14)
- Assigned tasks for pres 3
- Team Meeting (11/21)
- Cutoff for timelogs to be in presentation is Saturday midnight
- Deadline for slide submittal to Leanne is Friday midnight
- Team Meeting (11/28)
- Assigned parts of security presentation
- Team Meeting (12/5)
- Assembled final documentation CD
- Team Meeting (01/18)
- Assembled a proposal for functionality at each iteration
- Decided not to meet next Monday since there won't be anything to discuss by that point
- Team Meeting (01/23)
- performed PMA
- Decided to meet next Monday to hash out iteration schedules and prepare presentation for lab
- Team Meeting (01/29)
- created project schedule for iteration 1 (and skeleton for 2/3)
- Team Meeting (02/05)
- reviewed findings from the week's research
- decided to meet after lab on Tuesdays except on presentation weeks
- Team Meeting (02/13)
- reviewed progress from the week's coding efforts
- it was a boring week
- Team Meeting (02/20)
- assigned tasks to prepare for presentation 4
- Team Meeting (02/27)
- assigned tasks for the coming week
- discussed subversion branch usage
- Team Meeting (03/06)
- discussed research from the past week
- assigned tasks for the coming week
- Team Meeting (03/13)
- assigned tasks for the coming 2 weeks
- Team Meeting (03/20)
- no team meeting
- Team Meeting (03/27)
- made final plans for presentation 5 & assigned tasks
- Team Meeting (04/03)
- discussed plans for open house (meeting on monday at 3:30)
- Team Meeting (04/10)
- no decisions (prep for open house is complete)
- Email with dag (04/13)
- multiple levels will be created instead of making the propellers rotate for iteration 3
- Email with dag (04/15)
- Ogre libraries will be updated instead of creating multiple levels for iteration 3 since we were ahead of schedule
- Team Meeting (04/17)
- assigned tasks for the next 2 weeks
- Team Meeting (04/24)
- assigned tasks for presentation 6